Mayo-dawson city

transmission Project

The project involved the full design, procurement, construction, commissioning, training of client personnel and start-up of a 223 km transmission system (which included substations, a synchronous condenser, distribution under build, a diesel generator/grid transfer facility in Dawson and modifications to the hydropower generation source connection in Mayo).

Our work

  • Chant self-performed the design (lines and stations)
  • Provided overall project and construction management as the design-build contractor.

HIGHLIGHTS

  • Wooden pole transmission line structures with 36 km of under built distribution line. Governing span of 100 m.
  • Alignment changes during the work were necessary to capture additional power purchasers and address Placer Miner needs adjacent to the right of way.
  • The right of way included areas of poor ground conditions, environmentally sensitive soils (that required specific access strategies and working procedures) and permafrost conditions .
  • Substation design included the performance of extensive studies, engineering and coordination with Yukon Energy.  Chant was responsible for production of control logic, design briefs and drawings,  as-built drawings, operations and maintenance manuals and training operators in the system.